June - July 2013 Aug-Sept 2013 >>

Affected Areas:

1. Northwest Mall Landscape Construction, Phase 1
May 20 - August 8
The area indicated will be a construction zone and will be protected. This construction will affect pedestrian traffic. Any building entrances adjacent to the construction zone will be closed and other building entrances should be used.

2. Piping - Parking Lot Area F Phase 2
June 25 - July 9
The area indicated will be a construction zone and will be protected. This construction will affect pedestrian traffic and parking; parking will remain open to through traffic. Area F permit holders will be contacted directly.

3. Piping - Parking Lot Area F Phase 1
June 10 - June 24
The area indicated will be a construction zone and will be protected. This construction will affect pedestrian traffic and parking; parking will remain open to through traffic. Area F permit holders will be contacted directly.

4. Piping - Site Northeast of Library
June 20 - July 9
The area indicated will be a construction zone and will be protected. This construction will affect pedestrian traffic.

5. Piping - V.H. McNutt Hall to Computer Science Building
July10 - July 16
The area indicated will be a construction zone and will be protected. This construction will affect pedestrian traffic.

6. Piping -Engineering Research Lab to Straumanis James Hall
May17- June 7
The area indicated will be a construction zone and will be protected. This construction will affect pedestrian traffic.

7. Butler Carlton Civil Engineering Air Handler Coil Replacements
July 22 - July 24
This outage will affect specific rooms in this building. Occupants will be contacted directly for coordination of construction activities.

8. Piping - Engineering Management Building West to McNutt Hall.
July 18 - July 25
The area indicated will be a construction zone and will be protected. This construction will affect pedestrian traffic.

9. Piping - Parking Lot Area F Phase 3
July 10 - August 2
The area indicated will be a construction zone and will be protected. This construction will affect pedestrian traffic and parking; parking will remain open to through traffic. Area F permit holders will be contacted directly.

10. Piping -Site East of Norwood Hall and West fo Interdisciplinary Engineering Building
July 31- August 15
The area indicated will be a construction zone and will be protected. This construction will affect pedestrian traffic.

Z. Construction Staging Zone
February 1 - October 31
The area indicated will be a construction zone and will be protected. This construction will affect pedestrian traffic.

Updated 8/1/13