The geothermal project schedule is outlined below.  The system has been in operation since June 2014.

  • Approval by Board of Base Project and Bond Financing-November 2010
  • Design Consultant Selected-Early 2011
  • Construction Manager Selected-Fall 2011
  • Pre Purchase of material-December 2011
TaskStartEnd
Northeast Loop Well Fields & Geothermal Piping Mar 2012 Jun 2012
Northwest Loop Well Fields & Geothermal Piping May 2012 Aug 2012
South Loop Well Fields & Geothermal Piping July 2012 Oct 2012
Trenching & Individual Building Work Feb 2013 July 2014
Northeast Loop Plant Construction Feb 2013 Mar 2013
Northwest Loop Plant Construction Feb 2013 Apr 2014
South Loop Plant Construction Nov 2013 Jun 2014
Bertelsmeyer Hall Construction Jan 2013 Jun 2014

Decommission Power Plant

May 2014

Jun 2014